Someone asks why a beam depth changed on level 3 how does bidlight show one elem

1
Open the issue pinned to that beam. It carries the full trail: every time the element changed across published versions, who changed it, and the model commit that fixed it.
support@bidlight.com
asked 42 minutes agoSupport Team

Answers

0
<p>Open the issue pinned to that beam. It carries the full trail: every time the element changed across published versions, who changed it, and the model commit that fixed it.</p> <p>Here is how you get there:</p> <ol><li>In the Revit or Navisworks model, select the beam. Its issue opens.</li><li>The issue shows the version history for that element: each export compared element by element, so you see exactly when the depth changed.</li><li>You see the tagged user and the commit behind each change.</li><li>The 6am digest already told the owner what they own, so the right person is on it before the question reaches the field.</li></ol> <p>No more two-hour meetings spent working out who moved what. You get the answer in the model, tied to the element, with proof. That is how a change caught before it reaches the field stays a $50 fix instead of a $5,000 to $50,000 field problem, and why crews are not left idle at $15K to $50K a week while someone chases the story.</p> <p>One live record. One element. One history.</p>
support@bidlight.com
answered 42 minutes agoSupport Team

Your answer

Browse other questions tagged  or  ask your own question.